DRESDNER ROBIN was contracted by the City
of Jersey City to manage and deliver the successful completion
of the Waterfront Access Corridor Improvements to the intersection
of Christopher Columbus Drive and Washington Street.
The project involved reprofiling of the roadway and significantly
raising the intersection of Christopher Columbus Drive and
Washington Street to eliminate the hazardous flooding conditions
and allow emergency access. The project includes roadway reconstruction,
drainage improvements, new sidewalks, curbing, and streetscape
landscaping.
Our task was to provide construction coordination, on site
engineering and inspection services, track construction, monitor
the construction schedule and continuously update Critical
Path Schedule. DRESDNER ROBIN’s scope under the project
included tracking costs during construction, organizing, conducting
and documenting bi-weekly job meetings to ensure timely schedule
and conformance with the Contract Documents.
In the Pre-Construction Phase, Dresdner Robin staff engineers
reviewed the Contract Documents to provide recommendations
for adjustments or modifications to fit the work to local
conditions. Dresdner Robin reevaluated the street lighting
and prepared a lighting plan to continue the decorative lighting
pattern established in the adjacent area into the subject
access corridor. We provided recommendations and modifications
to the landscape plan to coordinate with the proposed lighting.
Dresdner Robin reengineered the drainage system to physically
work with the complex existing utilities and coordinated major
utility relocations and adjustments. We organized and compared
the bids and provided a recommendation for awarding the contract.
During construction Dresdner Robin reviewed shop drawings
and submittals and made recommendations for processing. We
evaluated and processed Change Order Requests, information
requests (RFI) and value engineering (VE) requests and suggestions
and maintained supporting documentation.
In the field Dresdner Robin monitored and coordinated quality
control testing, daily documented the work progress in project
records and with photos and video. We developed construction
deficiency lists and resolved the issues.
During the close out phase Dresdner Robin prepared a list
of outstanding work items, monitored construction through
final completion, reviewed as-built plans, manuals and warranties
provided by the contractor and assembled a final project record.
We certified to the City the Final Certificate of Payment.
|
|