Case Study

Wittpenn Bridge

Bridging Challenges and Solutions

Wittpenn Bridge

Line sag between electrical towers is a critical factor in designing and constructing electrical transmission facilities. During the construction of Wittpenn Bridge on Route 7 in Kearny, a concern was raised that light fixtures and highway signs were too close to existing high voltage electric transmission lines. So, Dresdner Robin was hired to survey the existing bridge during construction.

We used our 3D Laser Scanner to piece together a snapshot of the entire area in a point cloud. From this point cloud we were able to extract the transmission wires to determine their conformance with the design specifications.

We also identified the location of proposed bridge improvements in relation to where the high-voltage lines would sag under a worst-case scenario of maximum voltage and high temperatures. At the end of the day, our finished product was a single-sheet drawing clearly showing where the proposed improvements would fall in relation to the transmission wires.

  • SHARE:

CONTACT US

Dresdner Robin is a New Jersey certified Small Business Enterprise (SBE).

Jersey City

30 Montgomery Street,
Suite 510
Jersey City, NJ 07302

P: 201-217-9200

Fairfield

55 Lane Road, Suite 220
Fairfield, NJ 07004

P: 973-696-2600

Cherry Hill

Cherry Tree Corporate Center
535 Route 38 East, Suite 502-D
Cherry Hill, NJ 08002

P: 856-488-6200

contact-section